Building Construction


Pompano Beach Lift Sta 21 Replacement (12/2011)
City of Pompano Beach, 1201 NE 3 Avenue, Pompano Beach, FL  ::  Tammy Good, PM
Construction of Lift Station located within Single story 3800 sf building. This project includes auger pilings, cast in place below ground valve vault and pipe trench, sanitary sewer main replacement on DOT roadway, new force main, water main, landscaping, Structural, roofing, plumbing, electrical and various components

S-140 Pump Sta Refurbishment (3/2012)
South Florida Water Management, 3301 Gun Club Road, West Palm Beach, FL 33416
Pump station refurbishment of a South Florida Water Management District (SFWMD) stormwater pump station.  Selective demolition and replacement of precast concrete decking, overhaul (3) existing pumps and (3) gear boxes and install (3) new engines, install new generator, update refurbish electrical and instrumentation.


COMPLETED PROJECTS


Basins S-4 and S-5 Pumping Station (September 2001)
South Broward Drainage District, 6591 Southwest 160 Avenue, Davie, Florida 33331
Construct stormwater pump station with 96” Concrete pipe.

Baywinds Stormwater Pump Stations (September 4, 2000)
Northern Palm Beach County Improvement District, NPBCID Unit of Development 5B
Construct two Storm Water Pumping Stations and (2) directional bores of double 6” HDPE, one being being 1450 lf and another being 1400 lf.

D-Basins Pump Station (May 2000)
City of Oakland Park, 3650 N.E. 12th Avenue, Oakland Park, Florida 33334
Construct three lift stations D1, D2, and D4

Switchgear Bldg No. 2 – Structural Renovations (August, 1997)
City of Hollywood
The switchgear building was settling due to cracking in underground tank east of the structure. To correct we installed approx 70 pin piles through the floor slab or the building at the Wastewater Treatment Plan. Designed, built and ionstalled electrical switch gear Flood barrier doors, structural repairs to building, including epoxy wall cracks, repair stucco, seal floor and install barrier doors

Peanut Island Park (December 1999)
Palm Beach County Board of Commissioners
Construction of a boater’s park, with enhancement of water-oriented recreational facilities which include: A 10′ wide boardwalk around perimeter of the island, Family picnic Pavilions, restrooms with showers and drinking fountains. Campground with (28) campsites, Ranger station, a fifteen slip boat dock, fishing pier, Exotic native landscaping, site lighting and electrical service.

Electrical Power Generators ()
City of Hollywood, Department of Public Utilities, Engineering Support Services Division, P.O. Box 229045, Hollywood, Fl 33022-9045
Construction Power Generator Building and install two generators.

Rotary Park Boat Ramp and Boardwalk (July 1997)
City of Hollywood
Construct concrete boat ramp, boardwalk on wood piles, a wooden walk bridge, concrete walkways, picnic shelters and the installation of rip rap.